Pedestrian Zebra Crossing Installation - Completed October 2021
City of Darwin advises that zebra crossing installation works will be taking place on Smith Street in between Searcy Street and Peel Street, Darwin.
This is a project jointly funded by City of Darwin and the Australian Government under the Local Roads & Community Infrastructure program and to be delivered by the City of Darwin.
Works commenced 8 August 2021, with civil works scheduled to be complete 13 August 2021.
Works take place Sunday to Monday between the hours of 7.00am to 5.00pm.
Due to the increased traffic in the area, when works are occurring Smith Street will be closed in between Searcy Street and Peel Street, Darwin. Suitable pedestrian access will be maintained for the duration of the works.
Contractors will be using machinery that may cause a noise disturbance for the duration of the works.
Traffic control devices will be in place at all times to assist in the area.
We thank you in advance for your patience and consideration.
Responsible Officer: Mathew Vitucci, Senior Coordinator Project Delivery.