Coconut Grove
In progress
Project type
Stormwater
Stormwater Replacement Works – Martin Crescent, Coconut Grove
Scope of Works
Stormwater pipe replacement works on Martin Crescent, Coconut Grove. Please refer to the map below indicating the work area in red.
Project Timeline
- Start date: Monday 17 August 2026
-
Estimated completion date: Friday 23 October 2026 (Construction works were completed on 11 September, and the site is now in the establishment phase)
Project Benefits
These works form part of Council’s Annual Stormwater Upgrades and Reconstruction Program, aimed at replacing aged stormwater infrastructure to improve drainage performance, reduce flood risk, improve public safety, and minimise pollutants and ongoing maintenance costs.

08 8930 0300
darwin@darwin.nt.gov.au
Responsible Officer: Sara Webb, Project Officer